PR No. : 2013-068
Release Date : September 25, 2013
Reference : CHERYL R. TORTAL and EDWIN T. RIO
Head, Coop Promotions Section ISD Manager
Contact Nos. : 433-5475 / 435-3640 to 55 (Local No. 212 & 233)
Email Address : cenecopr@gmail.com
Website : www.ceneco.com.ph
The National Grid Corporation of the Philippines (NCGP) will shut down its Amlan-Mabinay 138KV Line 1 or 2 to conduct annual preventive maintenance on Saturday and Sunday, September 28 and 29, 2013, respectively. In effect, the load of Line-1 will be carried by Line-2, or vice versa, which will be under security limit to protect the system against collapse. Load shedding is most probable if the load of Amlan-Mabinay Line 1 or 2 will reach its security limit.
NGCP advised CENECO to conduct a parallel maintenance on the same time and date to help prevent unexpected power interruption. The following are the scheduled preventive maintenance of CENECO in response to NGCP’s request:
Date: September 28, 2013 – Saturday
Time: 8:00AM – 5:00PM
Reasons:
· Opening/re-tapping of 69kV jumper at structure 176 beside Panaogao Sub-station, Silay City;
· Replacement of rotten 69kV suspension insulators from Panaogao Sub-station to Silay Sub-station;
· Replacement of rotten primary pole at 21st Lacson Street, Bacolod City; and
· Tree trimming covering areas under Lopez (Silay) Feeders 1,2 and 3