Central Negros Electric Cooperative, Inc. (CENECO) informs its electricity consumers that, in order to ensure the stability of its distribution lines, maintenance activities will be conducted on December 14, Saturday, as follows:
Date: December 14, 2013 – Saturday
Time: 8:00 AM to 5:00 PM
Reasons:
Replacement of rotten double circuit primary poles from Alijis Substation to NGCP;
Stringing/Armoring and tying of 69KV Transmission Line from Mansilingan Rotonda to NGCP;
Opening/Closing of recloser in front of Canla-on View Subdivision, Murcia;
Opening/Closing of Air Break Switch (ABS) at Abuanan to transfer load portion of Alijis Feeder 3 to Sum-ag Feeder 2; and Tree trimming covering Alijis Feeder 3 and 7.